PAT E1 Gas Pipeline Detail Design
Client
Schlumberger Rustaveli Company Limited (Branch) – Georgia
Work Type
Survey / Design
Location
Georgia
Project Status
completed
Start Date
2018-12-27
End Date
2019-07-27
PAT E1 Gas Pipeline Detail Design
Processing route options and selection of final route; provision of topographical, geotechnical and hydrological surveys; elaboration of pipeline plan and profile, plan of crossings, typical drawings, work scopes, MTO, calendar schedule and organization chart of construction works. Obtainment of construction permit. Length of gas pipeline is 19.6 km.